Question 1
After a transmitter plate-supply fault, all identified energy sources are locked out and the prescribed discharge procedure is completed. A qualified engineer's correctly rated tester indicates zero volts on the 5 kV bus. The tester passed its known-live-source check before the measurement but fails that check immediately afterward. What is the status of the bus for repair work?
Show answer & explanation
Correct answer: B - Deenergization is unverified; repeat the voltage test with proven working equipment.